UTE Porto Sergipe

The Porto de Sergipe I Thermoelectric Plant, with a generation capacity of 1,551 MW, counts on three 7HA gas turbines and a steam turbine, manufactured by General Electric (GE), besides the other usual systems in a combined cycle plant: steam recovery boilers, condensers, cooling tower, water and effluent treatment systems, and substation. This is the first project in Brazil to receive the 7HA turbine model, considered today to be the most efficient available on the market.

For the contract in question ENESA Engenharia, supports commissioning, maintenance and assisted operation, in addition to the C4 package with electromechanical assembly of 3 HRSG boilers and Pipe Rack support.